Terawatt Infrastructure, a San Francisco-based company that builds and runs charging depots for electric and autonomous fleets, has announced four new sites in South San Francisco, Nashville, Miami and Dallas. In a press release dated 12 November 2026, the company says the four sites together add nearly 22 MW of dedicated charging capacity. It says that is enough to charge more than 3,000 vehicles per day.
Not all four sites are open yet. The publication GCN notes that each site also puts a concentrated block of demand on a single utility meter, which makes the local utility a key part of each project.
What is open and what is still planned
The company's release gives these details for each site:
- South San Francisco, California: a 6.6 MW site near San Francisco International Airport that supports one fleet's Bay Area operations.
- Nashville, Tennessee: a 4.5 MW site near Nashville International Airport that supports local fleet operations.
- Miami, Florida: a 3.5 MW site in the Design District/Wynwood area. The release says it opens "this quarter" and "will support" a commercial fleet operator.
- Dallas, Texas: a 7 MW site near Dallas/Fort Worth International Airport. The release says it "will go live this quarter".
Charged EVs, working from the same company announcement, reports that two of the depots are now operating and two are scheduled to open this quarter. Going by the release, those two are Miami and Dallas. GCN's report opens by saying Terawatt "opened" all four depots this week, but later in the same article it says the Miami and Dallas sites are still to open. The company's own wording supports the reading that only South San Francisco and Nashville are running now.
Terawatt says it handled development and construction at all four sites, including entitlements, utility interconnection and site design. It says it will also run operations and maintenance using its own Charge Management Software, energy management tools and a 24/7 operations and maintenance system.
The new sites add to what Terawatt describes as nearly 30 depots in active construction or development across 16 US markets, with more in planning. Chief executive and co-founder Neha Palmer said more sites are "on the way in 2027". The company also says its network has delivered more than 93 million miles of driving range and dispensed more than 30 million kWh. These are the company's own figures.
Who the depots serve
Terawatt names Waymo and Flexdrive by Lyft among its customers in general. It does not say which fleets use the four new depots. GCN notes that the announcement does not name them.
The sources also describe the customers differently. Terawatt's release refers to "fleet operations" and "a commercial fleet operator". Charged EVs describes the Nashville site as supporting "local AV operations" and says the Miami and Dallas sites will serve autonomous vehicle fleet operators. The Palmer quote in Charged EVs also mentions "autonomous" fleets, a word that does not appear in the version of the quote in the company release. It is not clear from the sources whether any of these depots are meant for driverless vehicles.
What depot charging asks of the grid
GCN notes that each depot puts a concentrated, around-the-clock load on a single utility meter. That is a very different pattern from scattered home charging. The publication says megawatt-scale fleet sites can rival the demand of a small industrial customer. It adds that utilities such as Pacific Gas and Electric (PG&E) are increasingly building dedicated engineering and permitting tracks for these connections rather than treating them as routine commercial hookups.
The South San Francisco site shows the role the utility plays. Terawatt says it finished the buildout ahead of schedule and cut costs "by six figures" through what it calls innovative site-energization methods and close collaboration with PG&E. In a blog post cited by GCN, PG&E said the project took 10 months from property acquisition to full energization, with 5 months taken off the timeline.
PG&E's figures do not exactly match Terawatt's. The utility describes the site as bringing nearly 7 megawatts of new charging capacity online, enough for up to 1,000 vehicles a day. Terawatt gives the site's capacity as 6.6 MW. The sources do not explain how the vehicles-per-day figures were calculated.
"Fleet electrification is growing quickly, and our job is to make sure the grid is ready to support it safely, reliably and efficiently," said Jason Glickman, executive vice president for strategy and growth at PG&E.
What to watch
The main open questions are whether the Miami and Dallas sites go live this quarter as planned, and whether the fleets using the depots will be named. The sources give interconnection timelines only for the PG&E project in California, not for the sites in Tennessee, Florida and Texas.
GCN expects the pattern seen in these four cities to repeat in other metropolitan areas: utilities working to speed up connections for high-power depots as logistics, delivery and autonomous-vehicle operators move to electric fleets.