Switzerland's Federal Roads Office (ASTRA, also known in English as FEDRO) has chosen the companies that will build the country's first dedicated charging network for electric trucks on national roads. Lot 1 goes to Fastned Switzerland, lot 2 to Obornes and lot 3 to Milence. According to electrive, the award covers 32 locations with a total of 82 truck charging stations at rest areas and heavy-vehicle control centres.
Switzerland sits on a north-south transit axis. Electrive calls it a European pioneer in electrifying heavy transport, with a relatively high number of electric trucks and a disproportionately high electric share among heavy trucks.
How the tender worked
ASTRA opened the call in January 2026. Dr. Web, citing ASTRA's project page, gives the start date as 5 January 2026 and the deadline for submissions as 30 April.
The reports give different counts of applications. Electrive reports eleven applications, which ASTRA says is more than in its earlier tenders. TIR transNews reports eleven valid applications. Dr. Web says ASTRA received 13 applications, of which 11 met the award criteria.
ASTRA says the lots went to the companies "whose submissions were rated highest, particularly in terms of construction quality and energy efficiency." According to Dr. Web, ASTRA's invitation document gave these weightings:
- Technical and construction quality: 40%
- Operational quality: 30%
- Applicant experience: 20%
- Energy efficiency and innovation: 10%
Lots 1 and 3 each have eleven fixed locations, and lot 2 has ten. ASTRA has already set the number of charging points at each site, and the figures vary widely. Campagnola, for example, gets two CCS points. The heavy-vehicle control centre at Rothenburg gets two MCS (megawatt charging) points and ten CCS points. Seven of the 32 sites will have at least one MCS point.
Each CCS point must deliver at least 350 kW. Dr. Web reports that this applies even when several trucks charge at once, and that each required MCS point must deliver at least 800 kW. Dr. Web adds that MCS points are required at strategic sites on the north-south transit axis. Fastned says it intends to offer at least 400 kW per charging point.
The operators pay for, build and run the chargers themselves. ASTRA provides the grid connections up to and including the transformer station and pays for them upfront. The operators then pay that money back to the federal government through an annual fee.
According to Dr. Web, ASTRA sets the connection capacity, and operators who want more, for example for extra MCS points, must pay the extra cost. Operators must also let drivers without a contract pay on the spot, without registering, and must show the price per kilowatt-hour before charging starts.
The three winners
Fastned, a Dutch company, has so far mainly invested in charging parks for cars. It says it has been building and running dedicated truck charging areas in Belgium and the Netherlands since 2025. Christine Zingg-Graf, Fastned's country director for Switzerland, said charging infrastructure "needs to keep pace with market developments."
Obornes, based in Aix-en-Provence, is a subsidiary of the Ortec Group, which builds and runs public high-power chargers under the Oreve brand. It has mainly worked in France.
Milence is a joint venture of Daimler Truck, Traton and the Volvo Group, founded in 2022. According to electrive, it has 42 charging parks across nine European markets, but none yet in Switzerland. Chief executive Anja van Niersen called Switzerland "a central hub for European freight transport" and said Europe "must significantly accelerate the rollout of charging infrastructure."
Why it matters for European freight
Electrive cites figures from auto-schweiz showing that 847 fully electric heavy commercial vehicles over 3.5 tonnes were newly registered from January to September, a market share of 27.4 per cent. Electrive compares the Swiss plan to Germany's planned network of 350 truck charging parks along its motorways, where the second tender round has just begun.
Dr. Web points out that from 2031, electric trucks in Switzerland will start paying the heavy vehicle charge, from which they have so far been exempt. At first they will get a discount of at least 70%.
The project is part of Switzerland's Electromobility Roadmap. According to TIR transNews, the roadmap has been extended to 2030 and brings together more than 70 players from transport, government, industry associations, environmental groups and science.
Timeline and what is still unknown
According to Dr. Web, the reservation agreements are due to be signed at the end of 2026. After that, the operators have two years to plan their projects and apply for building permits.
ASTRA expects the first stations to open in 2030 and all 82 to be available by 2035. Dr. Web reports that ASTRA requires each operator to have only three sites equipped by 2030 at the latest, with the rest following by 2035.
Dr. Web also notes that ASTRA's invitation document warns that the number and location of sites and charging points may still change during planning. The document also says ASTRA does not accept liability for delays caused by a lack of grid capacity or by permit procedures.
Dr. Web's publisher, Michael Dobler, wrote that a network whose first stations arrive in 2030 does not replace depot charging, and that hauliers ordering electric trucks now will charge on their own for the time being.