The UK had 124,738 public electric vehicle chargers on 1 October, according to the Department for Transport (DfT). Its quarterly statistics, published on 25 November 2026, show 8,686 chargers added so far in 2026, compared with 13,281 in the whole of 2025.

The network is still growing, but this year's additions so far are below last year's full-year total. The figures also show that most public chargers are slower units in towns and cities, with a smaller layer of fast charging on top.

What the figures show

The DfT says the 124,738 chargers work out at 180.0 per 100,000 people. Chargers rated rapid or above (50kW and over) numbered 29,772, or 42.9 per 100,000.

By power, 49% of chargers were standard (3kW to less than 8kW) and 27% were standard plus (8kW to less than 50kW). Rapid (50kW to less than 150kW) and ultra-rapid (150kW and above) chargers each made up 12%.

By location type, destination chargers at places such as supermarkets and retail parks made up 52% of the total, according to a summary by trade publication Forecourt Trader. On-street chargers made up 33%, and standalone hubs 11%.

Provision varies a lot by area. London has many more public chargers per person than the rest of the UK. However, it has the second-lowest number per person of chargers rated rapid or above, because much of its provision is standard on-street charging. Provision was typically higher than average in Scotland, Wales and the Greater London Authority. In England, 9,616 rapid or faster chargers were within one mile of the Strategic Road Network, and 8,857 of them were open-access.

Forecourt Trader reports that 83.2% of sockets are in urban areas and 16.8% in rural areas, and presents this as a UK-wide picture. Coverage by Primaryignition.com gives the 16.8% rural figure for England and Wales only, against 17.5% of the population living in rural areas.

The two summaries also differ slightly on the ratio of chargers to cars. Both cite one public charger for every 18 electric vehicles. Primaryignition.com says this figure applies at 1 July, not 1 October.

Jake Wardle, founder of EV Cable Hub, which sells charging cables, told Forecourt Trader that 96% of on-street chargers are slower posts rather than rapid chargers. He said most are sockets without a cable attached, so drivers need to bring the right cable.

How this year compares

The 8,686 chargers added in 2026 only cover the period up to 1 October, so they cannot be compared directly with a full year. The 2025 total of 13,281 was below the 24,557 added in 2024 and the 20,662 added in 2023. Those earlier figures are industry estimates from Zapmap and are not part of the official statistics.

Zapmap supplies the data behind the DfT figures. It says the 2025 additions grew the network by 13%, but fewer chargers were installed than the year before. It also says a change in how one network reported its data led to a net drop of about 500 chargers towards the end of 2025. Zapmap notes that among rapid and ultra-rapid chargers, new installations are shifting towards ultra-rapid.

Zapmap's own monthly count runs to the end of October. It shows 126,140 chargers at the end of October 2026, with 10,088 added so far in 2026, and 30,060 rapid or ultra-rapid chargers.

Chargers versus devices

The DfT now counts chargers rather than devices. One device can hold more than one charger. The department also counted 97,976 public charging devices, which it calls an older metric. It proposes to stop publishing the device count after February 2027, after a 12-month period of publishing both measures.

Zapmap made the same switch from devices to chargers for 2026 and renamed its power bands. The old "Slow" band is now "Standard" and "Fast" is now "Standard Plus". Readers comparing with older reports should keep this in mind.

What the data cannot show

The figures count chargers, not how much power they can deliver. Zapmap says rapid and ultra-rapid chargers make up only 24% of chargers but account for 80% of total capacity. It also says the number of chargers at a site is not a perfect measure of how many cars can charge there at the same time.

The grant figures in the same release are also incomplete. Statistics for the Local Electric Vehicle Infrastructure (LEVI) Fund, which helps English councils provide charging for residents without off-street parking, run three months behind the rest of the release. Because the latest three months of LEVI installations are estimated, the public charging grant figures are provisional.

The DfT's next quarterly report is scheduled for February 2027.